Case study background
AUTOMOTIVE CASE STUDY

Precision Automotive Timing Chain

Delivered 50,000 precision timing chains for a European Tier-1 automotive supplier in 6 weeks with 99.8% quality pass rate and full PPAP Level 4 documentation.

50,000Units Delivered
6Weeks Lead Time
99.8%Quality Pass Rate
18+Years manufacturing
0.8–18 mmCustom chain widths
30+Finishes available
100%Pre-shipment inspection
THE CHALLENGE BEGINS

Client Requirements

A European Tier-1 automotive supplier required a high-precision timing chain for a new engine platform.

Precision Requirements

Pitch tolerance of ±0.05mm across the full 50,000-unit run.

Documentation

Full PPAP Level 4 submission including PFMEA and control plans.

ENGINEERING HURDLES

Technical Challenges

The project presented several engineering challenges.

TP

Tight Pitch Tolerance

Maintaining ±0.05mm pitch tolerance required precision tooling.

WR

Wear Resistance

Timing chain demanded high wear resistance under high-temperature operation.

PD

PPAP Documentation

Full PPAP Level 4 required complete traceability.

ENGINEERING RESPONSE

Our Solution

We developed a complete engineering solution covering material, tooling, and process control.

Material Specification
01

Material Specification

Selected high-carbon C45 steel for optimal wear resistance.

Tooling Design
02

Tooling Design

Precision progressive die tooling with in-die sensors.

Process Control
03

Process Control

Real-time SPC monitoring with automated dimensional checks.

SAMPLING JOURNEY

Prototyping & Iterations

Three prototyping iterations refined the chain design.

First Prototype
Week 1-2

First Prototype

Initial sample on prototype tooling.

Engineering Sample
Week 3-4

Engineering Sample

Refined sample with updated tolerances.

Golden Sample
Week 5-6

Golden Sample

Final approved sample on production tooling.

QUALITY ASSURANCE

Testing & Validation

Comprehensive testing validated the chain performance.

DELIVERY EXCELLENCE

Mass Production Results

Mass production delivered on schedule with consistent quality.

50,000
Units Delivered

Across 6 weeks

99.8%
Quality Pass Rate

First-pass yield

100%
On-Time Delivery

Met all milestones

Production Timeline

Week 1-2
Tooling Setup
Week 3
Ramp-Up
Week 4-6
Full Production

Quality Metrics

Pitch Tolerance±0.05mm
Breaking Force6.5 kN
Wear Depth< 0.1mm
CONTINUOUS IMPROVEMENT

Lessons Learned

Key takeaways that inform continuous improvement.

01

Early Tooling Investment

Precision tooling reduced pitch variance by 40%.

02

SPC Integration

Real-time SPC caught 95% of process drift.

03

Documentation First

Building PPAP documentation streamlined submission by 30%.